Solution Design & Integration · Systems Architecture

Build vs buy

Reading30mLesson 3 of 3 in this module

What you'll learn

  • Score vendor options
  • Compare buy, configure, customise, build and hybrid options
  • Estimate total cost of ownership over several years
  • Apply must-have gates before a weighted scoring matrix

Compare building, buying and configuring a product, and score vendor options with a weighted matrix.

Why it matters

"Should we build it ourselves or buy a product?" is one of the most expensive decisions a project makes, and it is often made on gut feeling or on the best sales demo. Analysts bring structure: clear requirements, a fair comparison and a recorded rationale that someone can revisit in two years when the decision is questioned.

The options are wider than two

  • Buy (SaaS or packaged software): use the product largely as it comes. Fast to start, the vendor handles upgrades, but you adapt your process to the product.
  • Configure: buy a platform and set it up with settings, workflows and fields (most CRM and ERP projects).
  • Customise / extend: add code on top of a product. Powerful, but every customisation can break at upgrade time.
  • Build: write your own. Full control and fit, but you own every bug, upgrade and security patch forever.
  • Hybrid: buy the commodity parts and build the parts that differentiate you.

A useful rule of thumb: buy what is commodity, build what is differentiating. Payroll, email and accounting work the same way for nearly everyone; buy them. A unique pricing engine that wins you customers may be worth building.

Total cost of ownership

Compare costs over several years, not just the first invoice:

Buy:    licences/subscriptions x users x years
        + implementation partner + data migration + integrations
        + training + internal admin time
Build:  development team x duration
        + hosting + security and compliance work
        + ongoing maintenance (often 15-25% of build cost per year)
        + the opportunity cost of what that team is not building

The weighted scoring matrix

  1. Agree the criteria before you see demos, from the requirements: functional fit, integration (APIs available), security and compliance, total cost, vendor viability, usability, time to deliver.
  2. Weight them so they sum to 100%. Stakeholders agree the weights; this is where priorities become explicit.
  3. Score each option 1 to 5 against each criterion, using evidence: scripted demos (give vendors your scenarios), reference calls, a trial or proof of concept.
  4. Multiply and sum. The highest total is the recommendation, unless an option fails a must-have gate, which disqualifies it whatever its score.

Worked example: Harbor Outfitters CRM

Must-have gates: stores customer consent; has a documented REST API; can import 180,000 legacy customers.

CriterionWeightVendor A (SaaS CRM)Vendor B (CRM suite)Build in-house
Functional fit (loyalty, segments)30%455
Integration with NetSuite and Shopify20%533
5-year total cost20%422
Time to go live15%431
Usability for store staff15%434

Weighted totals (score x weight, summed):

Vendor A: 4(.30)+5(.20)+4(.20)+4(.15)+4(.15) = 1.2+1.0+0.8+0.6+0.6 = 4.20
Vendor B: 5(.30)+3(.20)+2(.20)+3(.15)+3(.15) = 1.5+0.6+0.4+0.45+0.45 = 3.40
Build:    5(.30)+3(.20)+2(.20)+1(.15)+4(.15) = 1.5+0.6+0.4+0.15+0.6 = 3.25

Vendor A wins clearly, even though Vendor B has the best features. The recommendation document records the scores, the evidence behind each, the risks (Vendor A's loyalty module is newer) and the mitigations (a 30-day proof of concept on loyalty before signing).

Beyond the score

Also check: data ownership and export (can you leave with your data?), where data is hosted, the vendor's security certifications (such as SOC 2 or ISO 27001), contract length and exit terms, and the product roadmap. Sensitivity test the result: if changing one weight by 5 points flips the winner, the decision is close and needs more evidence.

Common mistakes

  • Choosing criteria after the demos, which bends them toward the favourite.
  • Letting vendors run their own demo script instead of your scenarios.
  • Comparing year-one licence price against a build estimate without maintenance.
  • Heavy customisation of a bought product, which gives you the costs of both options.
  • No recorded rationale.

Quick recap

  • Options range from buy to configure, customise, build and hybrid; buy commodity, build differentiators.
  • Compare total cost of ownership over several years.
  • Use must-have gates plus a weighted matrix agreed before demos, scored with evidence.

Try it

The Do tab asks you to build a weighted matrix for a real decision.

Key terms (5)

Configure
Buying a platform and setting it up with settings, workflows and fields rather than writing code.
Total cost of ownership
The full cost of an option over several years, including implementation, integration, training, maintenance and admin time.
weighted scoring matrix
A table that scores each option against agreed criteria, multiplies by each criterion's weight and sums the results.
must-have
A gate requirement that disqualifies an option if it is not met, whatever its weighted score.
Sensitivity test
Changing a weight slightly to see whether the winner flips; if it does, the decision is close and needs more evidence.

Recap

  • Options range from buy to configure, customise, build and hybrid; buy commodity, build what differentiates you.
  • Compare total cost of ownership over several years, including maintenance.
  • Agree criteria and weights before demos, then score each option 1 to 5 with evidence.
  • Must-have gates disqualify an option whatever its score.
  • Record the rationale, risks and mitigations so the decision can be revisited.