Write a short, honest RAG status report that shows progress, risks and the decisions you need.
Why it matters
Sponsors and stakeholders cannot watch the work every day. A status report is how they find out whether the project is on track and whether they need to act. A good one takes two minutes to read and leads to decisions. A bad one is ten pages of activity lists that nobody reads, or a cheerful "all fine" every week until suddenly it is not.
What a status report is for
A status report answers four questions for its readers:
- Are we on track? (overall status)
- What happened since last time, and what is next?
- What could go wrong, or has gone wrong? (top risks and issues)
- What do you need to do? (decisions or help needed)
Everything else is optional. Busy sponsors read the top, so put the answer first, just like the plain-language rule from the professional communication course.
RAG status
RAG stands for Red, Amber, Green, a traffic-light rating used for the overall project and often for each dimension (schedule, cost, scope, risk). Definitions must be agreed in advance, or everyone means something different. A common set:
- Green: on track. Any problems can be handled within the team's plan and contingency.
- Amber: at risk. There is a problem the team is working on that threatens a milestone, the budget or scope, but there is a credible recovery plan. The sponsor should be aware.
- Red: off track. A milestone, budget or scope target will be missed without a decision or help from outside the team.
Many organisations add numeric thresholds, for example: Amber if the forecast end date slips up to 5 working days or cost forecast exceeds budget by up to 5%; Red beyond that. Use your organisation's definitions if it has them.
Some teams add Blue for complete.
Honesty and watermelons
A watermelon project is green on the outside and red on the inside: the report says green while the team knows it is in trouble. It happens because people fear bad news or hope to recover quietly. It is the most damaging status-reporting habit, because by the time the truth appears, the cheap options are gone.
Turning amber early is a sign of good management, not failure. It gives the sponsor time to help. Report the forecast, not just the past: "We have done 60% of the work" is history; "At the current rate we will launch on 6 March, not 1 March" is what the sponsor needs.
A worked example
Food bank volunteer sign-up site: status, week 5 of 8 (7 February)
Overall: AMBER (was Green)
Forecast launch 6 March vs plan 1 March. Recovery plan below.
Status Note
Schedule Amber Design approval 4 days late (photos arrived 19 Jan)
Cost Green USD 2,100 spent of 3,850; forecast 3,700
Scope Green No changes since week 2
Risks Amber R3 adoption risk unchanged; R1 photo risk closed as issue
Done since last report
- Shift calendar and sign-up form built and tested on 2 of 3 phones
- Coordinator reviewed the CSV export: approved
Next two weeks
- Admin screen, accessibility check, coordinator guide draft
Top risks and issues
- Issue: design approval late (R1 happened). Recovery: second developer
starts the admin screen in parallel; saves 3 of the 4 days.
- R3 (score 12): low volunteer adoption. Paper fallback agreed for March.
Decision needed (by 10 February)
- Accept a 6 March launch, OR approve USD 300 of extra contractor
hours to hold 1 March.
Everything a sponsor needs is in the first three lines, and the decision has options and a deadline.
Format and rhythm
- Short: one page or one screen. Link to the details (schedule, risk register) rather than pasting them.
- Regular: weekly or every two weeks, on the same day. Predictability builds trust.
- Consistent: same headings each time, so readers can compare.
- Tailored: the board might get the overall RAG and decision only; the team gets more detail.
- Delivered with a conversation when the status is amber or red. Never let a sponsor discover red in an email.
Common mistakes
- Activity lists instead of outcomes ("attended 6 meetings").
- Undefined colours, so green means different things to different people.
- Watermelon reporting.
- No forecast, only what happened.
- Asking for a decision without options or a date.
Quick recap
- Status reports answer: on track? progress and next steps? risks and issues? decisions needed?
- RAG ratings need agreed definitions; amber early is good management.
- Report the forecast, keep it to one page, and send it on a regular rhythm.
Try it
Open the Do tab and write a one-page RAG status report for your project.